Linux Cluster: Delays in bringing Cluster segments to user operation
LRZ aktuell
publish at lrz.de
Mi Nov 9 17:58:13 CET 2011
Dear users of the Linux Cluster Systems at LRZ,
Unfortunately, return of the MPP cluster to user operation (originally
planned for November 11) as well as the start of operation of the new
Ultraviolet Cluster segments (originally planned for early November)
will be delayed.
For both the MPP cluster and the UltraViolet systems, we are now
targeting November 23 for return to user operation. This assumes that
we do not run into further, presently unknown technical issues.
Apart from the technical problems we have encountered both in moving
the MPP cluster to its new location and in performing software
integration of the SLURM queuing system with sgi's system software on
the Ultraviolet, the presently very constrained LRZ staff resources
have also contributed to the delays.
This information is also available on our web server
http://www.lrz-muenchen.de/services/compute/aktuell/ali4157/
Reinhold Bader
Mehr Informationen über die Mailingliste aktuell