Upd:SuperMUC: scheduled maintenance Jan 28 31
LRZ aktuell
publish at lrz.de
Do Jan 31 17:52:19 CET 2013
Changes to this message: Prolongation of maintenance
Update 2 (Jan 31 17:50): Internal testing unfortunately has revealed a
number of problems that prevent us from returning the SuperMUC system
to user operation. We intend to provide daily updates on the status of
the system.
-----------------------------------------------------------------------
Update (Jan 30 afternoon): In order to check additional hardware and
firmware modifications that were done to improve the stability of the
system (see also http://www.lrz.de/services/compute/supermuc/aktuell/
ali4512/, as well as dedicated operation for a project that requires
short-term use of the complete machine, user operation of the system is
delayed to the afternoon of January 31.
-----------------------------------------------------------------------
Dear users of the SuperMUC petascale system at LRZ,
Due to a combined hard- and software maintenance, SuperMUC will be
unavailable for user operation between January 28, 8:00 and the
afternoon of January 31. Jobs still running at the beginning of the
maintenance will be cancelled.
The following changes are introduced by this maintenance:
* Access to the PRACE network will become available to PRACE users,
* LoadLeveler mail notification will be activated,
* Licence servers will be accessible from the compute nodes,
* The Infiniband software stack will be updated to a newer release,
* Some presently missing packages will become available on the
compute nodes (e.g., you can remove the workaround for a missing
libnuma.so)
This information is also available on our web server
http://www.lrz-muenchen.de/services/compute/supermuc/aktuell/ali4502/
Reinhold Bader